Filling out a summary estimate. Consolidated estimate calculation - estimates - examples of estimates. Summary estimate by chapter

What is a summary estimate?

Documents that determine the estimated limit of funds - the cost of the full list of works (costs) required to complete all construction projects provided for by the project - are called summary estimates. The resulting calculation contains estimated cost not only construction and installation work, but also the costs of purchasing tools, inventory, equipment, as well as other associated costs, including designer supervision, survey work, maintenance of the customer service, etc.. It is easiest to draw up a consolidated estimate (abbreviated as SSR) using special estimate programs, but MS Excel is often used for this. In any case, the sample presented in methodological recommendations Gosstroy of the Russian Federation.

General provisions, which determines the content of the summary estimate

Main legal document regulating the procedure for compiling a summary estimate documentation, becomes the Methodology of the State Construction Committee (MDS 81-35.2004), approved and put into effect by Resolution No. 15/1 of the State Construction Committee of the Russian Federation in 2004 in the current edition, which the surveyors are guided by (on this moment, this is the 2014 edition).

The general provisions of the Methodology state that summary estimates of the cost of construction of objects (or their phases) include documents that determine the estimated limit of the funds needed for the complete completion of all objects under the project.

These same approved documents become the basis for starting the financing of the construction process and determining the limit capital investments. In summary form, recommendations for drawing up consolidated estimates can be presented in the following list:

This calculation is made at the current price level. The final decision on determining the price level, which is made when drawing up the SSR, remains with the customer and is recorded in the design assignment. At the same time, in general view To formalize the value at the current price level, it is proposed, as an option, to use the base level of 2001, indexed according to current index tables (within the framework of existing recalculation methods).

A consolidated estimate must be generated for the construction as a whole (regardless of the number of general contractors performing construction and installation functions in the project).

The estimated cost of work (costs) performed by each general contractor is entered into a separate statement. Such registration is carried out in relation to the SSR form.

Compilation of SSR by chapters

According to the recommendations of the Methodology, the consolidated estimate includes chapters into which funds for construction (or major repairs) are distributed based on calculations of its cost. In total, there are 12 such chapters - for industrial and civil construction and 9 - for major repairs of communal and socio-cultural buildings, as well as residential buildings. If any chapter provides for the inclusion of a particular object, work (cost), but in fact they are absent, then such a chapter should be skipped without changing the numbers of subsequent chapters.

Chapter 1. “Preparation of the construction site.” For the overhaul of communal, residential and socio-cultural facilities - the title of the first chapter mentions the preparation of the territory (sites) for overhaul.

Chapters 2 and 3. “Main construction objects” and “Ancillary and service objects”. (These two chapters are similar in both lists.)

Chapters 4 and 5 of the “construction section” have no analogues in the list of chapters for capital repair facilities and relate to “Energy Facilities” and “Transport Facilities” of construction.

Chapter 6 of the first list is similar to Chapter 4 of the second list and concerns external networks, as well as water, heat and gas supply structures, sewerage, etc. With the same two-point offset are the next three chapters, the same for both lists: “Improvement and landscaping” , “Temporary structures and buildings”, “Other work (costs)”.

The next, 10th chapter, in the list of “construction section” is the estimate for the maintenance of customer services (technical supervision), the 11th chapter is the preparation of operating personnel. The penultimate chapter of the SSR for overhaul facilities concerns the calculation of estimates for technical supervision services. The final chapter is the same for both lists. Its contents include designer supervision and design and survey work.

Within the listed chapters, the distribution of works (costs) and objects occurs in accordance with the established industry nomenclature. If there are several types of completed production with several objects for each of them, within the chapter it is allowed to rearrange the work (costs) and objects into sections with a name similar to the name of the production. For certain types of construction and industrial sectors, the names and nomenclature of the chapters of the SSR may change.

As part of the project, a documented SSR is submitted for approval along with an explanatory note. The contents of the note include the following information:

about the location of construction,

name of the contractor (if known),

list of accepted items for budgeting catalogs of standards, norms of estimated profit and overhead costs by type of construction (or for a specific contractor),

specifics of determining the estimated cost of construction work, equipment (including its installation),

features of the distribution of funds for construction according to Chapters 8-12 of the SSR and in the areas of capital investments for construction of a housing and civil nature.

In addition, the note lists any other information related to determining the cost of expenses specific to a given construction project, links to decisions of government agencies related to pricing issues and benefits for specific construction.

Summary estimate form: sample and example

To formulate a summary estimate, it is recommended to use sample No. 1, given in the second appendix of the Methodology, which was compiled by the State Construction Committee of the Russian Federation. In separate lines it includes the totals for all object estimates without citing the amounts spent to cover limited costs, and the totals for calculations for individual types of costs.

The document provides a reference to the numbers of these derivatives estimate documents. The cost of each object envisaged by the project is distributed according to the corresponding columns of the form. Columns 4-7 indicate how much the estimated cost is for construction (repair and construction) work (column 4), installation work (column 5), equipment costs (column 6), and other costs (column 7). Column 8 shows the total estimated cost. The summary estimate, an example of which is presented here, was compiled in MS Excel according to the specified sample.


Estimate for the construction of an apartment-type dormitory, including: preparation of the construction site, main construction objects, energy facilities, external power supply and electric lighting networks, external communication networks, transport and communication facilities, external networks and structures of water supply, sewerage, heat supply and gas supply, landscaping and landscaping, temporary buildings and structures, other work and costs, technical supervision, customer costs for putting the facility into operation, additional construction costs when carrying out work in winter time, design work, etc.
2016-02-04 | popularity: 8851
  • Consolidated estimate for major repairs of a residential building
    Consolidated estimate for the overhaul of a residential building (according to TSN-2001 Moscow), including calculations: selective overhaul of a house, main construction projects, overhaul of a residential building, funds for the construction of temporary buildings and structures, funds for the creation insurance fund construction organization, maintenance of the directorate (technical supervision) of the enterprise (structure) under construction, funds to reimburse the costs of maintaining the service of the customer-developer, attracted by the state investor to implement the state order for construction, design and survey work, designer's supervision, funds to pay for the pre-design examination and design and estimate documentation, approval of design and estimate documentation, funds to reimburse expenses for unforeseen work and expenses, funds to cover the costs of paying VAT, funds to pay design work and etc.
    2015-11-26 | popularity: 11712
  • Estimate for major repairs of external street lighting in Kazan
    Consolidated estimate for the overhaul of external street lighting, including: dismantling of reinforced concrete poles of overhead lines 0.38, 6-10 kV with traverses without single-column attachments, dismantling of intermediate, free-standing, single-column steel supports, installation of intermediate, free-standing, single-column steel supports, weighing up to: 2 t MKS-1.0-9, installation of reinforced concrete supports of overhead lines 0.38, 6-10 kV with traverses without attachments, drilling holes with crane drilling machines on a car up to 2 m deep, Device concrete foundations general purpose for columns with volume: up to 3 cubic meters. dismantling of wires on traverses on metal and reinforced concrete supports, special brackets on supports for lamps, lamps installed outside buildings, cables suspended on a cable, a clamp on a support, connection of wires or cables to the terminals of wires or cables, a cabinet-style control unit or distribution point (cabinet) ), installed on the wall, metal sleeve, tightening of wires into laid pipes and metal sleeves, first single-core or multi-core wire in a common braid, metal casing to protect inputs and electrical equipment, oil painting of metal surfaces: gratings, frames, pipes with a diameter of less than 50 mm, cables in a polyvinyl chloride sheath, brand VVG, vibrating stands for supports, protective casings, stand for PV, embedded part without flange, with flange, flanged support ZhRFI, lamps, SIP AMK-X, flange KS-9f, supports, clamps SL, SO , SOT 29 hooks, SJ couplings, buckles, etc.
    2013-06-20 | popularity: 11734
  • Summary estimate of the cost of boiler house construction
    Summary estimate of the cost of construction of a modular boiler house MKG-6 on gas fuel at Lenin Street 60/1: preparation of the construction site, main construction objects, energy facilities, external networks and water supply, sewerage, heat supply and gas supply structures, landscaping and landscaping, temporary buildings and structures, other work and costs, maintenance of the directorate, design and survey work, unforeseen costs, etc.
    2013-03-03 | popularity: 16352
  • Summary estimate for the object of the Central District Hospital Maternity ward
    Overhead costs are accepted according to MDS 81-33.2004
    Estimated profit according to MDS 81-25.2001
    Estimates are based on:
    a) TERM for construction work related to the local conditions of industrial and civil construction projects in the Saratov region, registered by the State Construction Committee of Russia NZ-3418/10 dated 06/04/03.
    b) FER for installation work
    c) Collections of average regional prices, parts 1-V-TSC
    d) Collection of zonal estimated prices for local building materials, products and structures of industrial and civil construction in the Saratov region" (SZSC-2001).
    e) The cost of machinery and equipment is taken at wholesale prices introduced on January 1, 1982. Using conversion indices to 2001 prices. According to the magazine KO "Invest" for 2003.
    f) The scope of work is calculated based on the detailed design drawings. The consolidated estimate has been recalculated into current prices for 2007. Using indices that take into account changes in the estimated cost of construction and installation work, equipment and other costs in accordance with the conversion index.
    2012-11-23 | popularity: 10012
  • Estimate documentation for the construction of a car pavilion
    The estimate documentation was compiled in accordance with MDS81-35.2004 “Guidelines for determining the cost of construction products in the territory Russian Federation».
    Estimated cost of construction, installation and repair construction work determined according to TER-2001, TERr-2001, TERm-2001 for the Lipetsk region, approved by resolution of the administration of the Lipetsk region, developed at the price level for the Lipetsk region as of January 1, 2000.
    Overhead costs are accepted by type of work according to “ Methodical instructions on determining the amount of overhead costs in construction" MDS81-33.2004
    The estimated profit is determined by type of work in accordance with the “Methodological guidelines for determining the amount of estimated profit in construction” MDS81-25.2001 SSRSS recalculated into current prices in accordance with the “Price Indices in Construction” of the Department of Architecture and Construction of the Lipetsk Region Administration.
    2012-11-23 | popularity: 11597
  • Estimate for reconstruction of the boiler room
    Local estimate calculation. Includes calculation sections AVK, AS, ATM, VK, GP, GSV, MS, OV, PNR, TM, EM, summary estimate calculation
    2012-04-16 | popularity: 24112
  • Share a link to the material in social network: Would you like to post an estimate? on our website? Write to us about it.

    Documents that determine the estimated limit of funds - the cost of the full list of works (costs) required to complete all construction projects provided for by the project - are called summary estimates. The prepared calculation contains the estimated cost of not only construction and installation work, but also the cost of purchasing tools, inventory, equipment, as well as other associated costs, including designer supervision, survey work, maintenance of the customer’s service, etc. Draw up a summary estimate ( abbreviated as SSR) is easiest using special costing programs, but MS Excel is often used for this. In any case, the sample presented in the methodological recommendations of the State Committee for Construction of the Russian Federation is taken as a basis.

    General provisions defining the content of the summary estimate

    The main legal document regulating the procedure for drawing up documentation becomes the Methodology of the State Construction Committee (MDS 81-35.2004), approved and put into effect by Resolution No. 15/1 of the State Construction Committee of the Russian Federation in 2004 in the current version, which the surveyors are guided by (at the moment, this is - edition 2014).

    The general provisions of the Methodology state that summary cost construction of objects (or their phases) include documents that determine the estimated limit of the funds that are needed for the complete completion of all objects under the project.

    These same approved documents become the basis for starting the financing of the construction process and determining the capital investment limit. In summary form, recommendations for drawing up consolidated estimates can be presented in the following list:

    1. It is recommended that a consolidated estimate be drawn up and approved separately for production and non-production construction work.
    2. This calculation is made at the current price level. The final decision on determining the price level, which is made when drawing up the SSR, remains with the customer and is recorded in the design assignment. At the same time, in general terms, to formalize the value at the current price level, it is proposed, as an option, to use the base level of 2001, indexed according to current index tables (within the framework of existing recalculation methods).
    3. A consolidated estimate must be generated for the construction as a whole (regardless of the number of general contractors performing construction and installation functions in the project).
    4. The estimated cost of work (costs) performed by each general contractor is entered into a separate statement. Such registration is carried out in relation to the SSR form.

    Compilation of SSR by chapters

    According to the recommendations of the Methodology, the consolidated estimate includes chapters into which funds for construction (or major repairs) are distributed based on calculations of its cost. In total, there are 12 such chapters - for industrial and civil construction and 9 - for major repairs of communal and socio-cultural buildings, as well as residential buildings. If any chapter provides for the inclusion of a particular object, work (cost), but in fact they are absent, then such a chapter should be skipped without changing the numbers of subsequent chapters.

    The next, 10th chapter, in the list of “construction section” is the estimate for the maintenance of customer services (technical supervision), the 11th chapter is the preparation of operating personnel. The penultimate chapter of the SSR for overhaul facilities concerns the calculation of estimates for technical supervision services. The final chapter is the same for both lists. Its contents include designer supervision and design and survey work.

    Within the listed chapters, the distribution of works (costs) and objects occurs in accordance with the established industry nomenclature. If there are several types of completed production with several objects for each of them, within the chapter it is allowed to rearrange the work (costs) and objects into sections with a name similar to the name of the production. For certain types of construction and industrial sectors, the names and nomenclature of the chapters of the SSR may change.

    As part of the project, a documented SSR is submitted for approval along with an explanatory note. The contents of the note include the following information:

    • about the location of construction,
    • name of the contractor (if known),
    • a list of standards catalogs accepted for drawing up estimates,
    • norms of estimated profit and overhead costs by type of construction (or for a specific contractor),
    • specifics of determining the estimated cost of construction work, equipment (including its installation),
    • features of the distribution of funds for construction according to Chapters 8-12 of the SSR and in the areas of capital investments for construction of a housing and civil nature.

    In addition, the note lists any other information related to determining the cost of expenses specific to a given construction project, links to decisions of government agencies related to pricing issues and benefits for specific construction.

    Summary estimate form: sample and example

    To formulate a summary estimate, it is recommended to use sample No. 1, given in the second appendix of the Methodology, which was compiled by the State Construction Committee of the Russian Federation. In separate lines it includes the totals for all object estimates without citing the amounts spent to cover limited costs, and the totals for calculations for individual types of costs.

    The document contains a link to the numbers of these derivative estimate documents. The cost of each object envisaged by the project is distributed according to the corresponding columns of the form. Columns 4-7 indicate how much the estimated cost is for construction (repair and construction) work (column 4), installation work (column 5), equipment costs (column 6), and other costs (column 7). Column 8 shows the total estimated cost. The summary estimate, an example of which is presented, was compiled in MS Excel according to the specified sample.

    The summary estimate is essentially one of the main documents on which the entire cost of construction work on the project is based. It includes not only materials and work, but also the tools, equipment necessary for purchase, and its rental, if required. Also, in addition to this, it includes all related work that must be performed to complete construction according to the project. This may include technical supervision, various approvals, territory cleaning, etc. You can see an example below.

    Navigation

    What is a consolidated estimate in construction? The cost of what work is included in it, refundable amounts in the calculation

    Documents that determine the estimated limit of funds - the cost of the full list of works (costs) required to complete all construction projects provided for by the project - are called summary estimates.

    The prepared calculation contains the estimated cost of not only construction and installation work, but also the cost of purchasing tools, inventory, equipment, as well as other associated costs, including designer supervision, survey work, maintenance of the customer service, etc. Draw up a summary estimate calculation (abbreviated as – SSR) is easiest with the help of special estimate programs, but MS Excel is often used for this.

    General provisions defining the content of the summary estimate

    The main legal document regulating the procedure for drawing up consolidated estimate documentation becomes the Gosstroy Methodology (MDS 81-35.2004), approved and put into effect by Resolution No. 15/1 of the Gosstroy of the Russian Federation in 2004 in the current version, which is what estimators are guided by (at the moment, This is the 2014 edition).

    The general provisions of the Methodology state that summary estimates of the cost of construction of objects (or their phases) include documents that determine the estimated limit of the funds needed for the complete completion of all objects under the project.

    These same approved documents become the basis for starting the financing of the construction process and determining the capital investment limit. In summary form, recommendations for drawing up consolidated estimates can be presented in the following list:

    1. It is recommended that a consolidated estimate be drawn up and approved separately for production and non-production construction work.
    2. This calculation is made at the current price level. The final decision on determining the price level, which is made when drawing up the SSR, remains with the customer and is recorded in the design assignment. At the same time, in general terms, to formalize the value at the current price level, it is proposed, as an option, to use the base level of 2001, indexed according to current index tables (within the framework of existing recalculation methods).
    3. A consolidated estimate must be generated for the construction as a whole (regardless of the number of general contractors performing construction and installation functions in the project).
    4. The estimated cost of work (costs) performed by each general contractor is entered into a separate statement. Such registration is carried out in relation to the SSR form.

    Compilation of SSR by chapters

    According to the recommendations of the Methodology, the consolidated estimate includes chapters into which funds for construction (or major repairs) are distributed based on calculations of its cost. In total, there are 12 such chapters - for industrial and civil construction and 9 - for major repairs of communal and socio-cultural buildings, as well as residential buildings. If any chapter provides for the inclusion of a particular object, work (cost), but in fact they are absent, then such a chapter should be skipped without changing the numbers of subsequent chapters.

    • Chapter 1. “Preparation of the construction site.” For the overhaul of communal, residential and socio-cultural facilities - the title of the first chapter mentions the preparation of the territory (sites) for overhaul.
    • Chapters 2 and 3. “Main construction objects” and “Ancillary and service objects”. (These two chapters are similar in both lists.)
    • Chapters 4 and 5 of the “construction section” have no analogues in the list of chapters for capital repair facilities and relate to “Energy Facilities” and “Transport Facilities” of construction.
    • Chapter 6 of the first list is similar to Chapter 4 of the second list and concerns external networks, as well as water, heat, gas supply, sewerage, etc.
    • With the same shift of two points, there are the next three chapters, the same for both lists: “Improvement and landscaping”, “Temporary structures and buildings”, “Other work (costs)”.

    The next, 10th chapter, in the list of “construction section” is the estimate for the maintenance of customer services (technical supervision), the 11th chapter is the preparation of operating personnel. The penultimate chapter of the SSR for overhaul facilities concerns the calculation of estimates for technical supervision services. The final chapter is the same for both lists. Its contents include designer supervision and design and survey work.

    Within the listed chapters, the distribution of works (costs) and objects occurs in accordance with the established industry nomenclature. If there are several types of completed production with several objects for each of them, within the chapter it is allowed to rearrange the work (costs) and objects into sections with a name similar to the name of the production. For certain types of construction and industrial sectors, the names and nomenclature of the chapters of the SSR may change.

    As part of the project, a documented SSR is submitted for approval along with an explanatory note. The contents of the note include the following information:

    • about the location of construction,
    • name of the contractor (if known),
    • a list of standards catalogs accepted for drawing up estimates,
    • norms of estimated profit and overhead costs by type of construction (or for a specific contractor),
    • specifics of determining the estimated cost of construction work, equipment (including its installation),
    • features of the distribution of funds for construction according to Chapters 8-12 of the SSR and in the areas of capital investments for construction of a housing and civil nature.

    In addition, the note lists any other information related to determining the cost of expenses specific to a given construction project, links to decisions of government agencies related to pricing issues and benefits for specific construction.

    Summary estimate form: sample and example

    To formulate a summary estimate, it is recommended to use sample No. 1, given in the second appendix of the Methodology, which was compiled by the State Construction Committee of the Russian Federation. In separate lines it includes the totals for all object estimates without citing the amounts spent to cover limited costs, and the totals for calculations for individual types of costs.

    The document contains a link to the numbers of these derivative estimate documents. The cost of each object envisaged by the project is distributed according to the corresponding columns of the form. Columns 4-7 indicate how much the estimated cost is for construction (repair and construction) work (column 4), installation work (column 5), equipment costs (column 6), and other costs (column 7). Column 8 shows the total estimated cost. The summary estimate, an example of which is presented here, was compiled in MS Excel according to the specified sample.

    Source: https://proektoved.com/rashody/svodnyj-smetnyj-raschet.html

    Summary estimate by chapter

    To reflect full cost of all work and costs provided for by the project, including the estimated cost of construction and installation work, the cost of purchasing equipment, tools, inventory, as well as all related costs, a consolidated estimate of the cost of construction is drawn up.

    In the summary estimate, funds are distributed among chapters and columns, depending on the nature of the work and costs.

    Chapters of the consolidated estimate:

    • 1. Preparation of the construction area.
    • 2. Main construction objects.
    • 3. Objects for auxiliary and service purposes.
    • 4. Energy facilities.
    • 5. Transport and communication facilities.
    • 6. External networks and structures of water supply, sewerage, heat supply and gas supply.
    • 7. Improvement and landscaping of the territory.
    • 8. Temporary buildings and structures.
    • 9. Other work and costs.
    • 10. Contents of the directorate (technical supervision) of the enterprise (institution) under construction.
    • 11. Training of operational personnel.
    • 12. Design and survey work, designer's supervision.

    The distribution of objects, work and costs within the chapters is carried out according to the nomenclature of the consolidated construction estimate established for the relevant sector of the national economy. If there are several types of completed productions or complexes, each of which has several objects, grouping within the chapter can be carried out into sections, the name of which corresponds to the name of the productions (complexes).

    For objects overhaul residential buildings, communal and social facilities cultural purposes as part of the summary budget calculation of funds it is recommended distributed over 9 chapters:

    1. “Preparation of sites (territories) for major repairs.”
    2. “Main objects”.
    3. “Objects for auxiliary and service purposes.”
    4. “External networks and structures (water supply, sewerage, heat supply, gas supply, etc.).”
    5. “Improvement and landscaping of the territory.”
    6. “Temporary buildings and structures.”
    7. “Other work and costs.”
    8. "Technical Supervision".
    9. “Design and survey work, designer’s supervision.”

    The consolidated estimate is drawn up for the entire construction, regardless of the number of general contracting construction and installation organizations participating in it.

    The estimated cost of work and expenses to be carried out by each general contracting organization is drawn up in a separate statement, compiled in relation to the form of the consolidated estimate.

    For the summary estimate submitted for approval as part of the project, a explanatory note , which provides the following data:

    Construction location;

    List of catalogs estimate standards adopted for drawing up construction estimates;

    Name of the general contractor(if it is known);

    Overhead cost rates (for a specific contractor or by type of construction) in accordance with MDS 81-4.99;

    Estimated profit standard according to MDS 81-25.2001;

    Features of determining the estimated cost of construction work for a given construction site;

    — features of determining the estimated cost of equipment and its installation for a given construction site;

    Features of determining funds for a given construction project according to Chapters 8 - 12 of the consolidated estimate;

    — calculation of the distribution of funds in areas of capital investment (for housing and civil construction, if they are determined by the design assignment);

    - other information on the procedure for determining cost specific to a given construction project, as well as links to relevant decisions of government and other public authorities on issues related to pricing and benefits for specific construction.

    The summary estimate of the cost of construction contains (in columns 4-8) the following results: for each chapter (if there are sections in the chapter - for each section), for the sum of chapters 1-7, 1-8, 1-9, 1-12, as well as after accruing the amount of the reserve for unforeseen work and expenses - “Total according to the consolidated estimate.”

    The consolidated estimate for capital repairs provides the final data for each chapter, for the sum of chapters 1-5, 1-6, 1-7, 1-9, as well as after accruing the amount of the reserve for unforeseen work and costs - “Total for the consolidated estimate calculation."

    The composition of the work and costs included in chapters 1,8,9 of the consolidated estimate and the procedure for their determination.

    Other costs are an integral part of the estimated cost of construction, are included in a separate column of the estimate documentation in the current price level and can relate to both construction as a whole and to individual objects and works, are taken into account in chapters 1 and 9 of the consolidated estimate in column 7 in the form of a limit of funds , spent by the customer to reimburse the relevant costs.

    For the projected construction, the composition of these works and costs should be clarified based on specific local conditions implementation of construction.

    Tools included in Chapter 1 “Preparation of the construction site”.

    1. Decor land plot and marking works:

    1.1. The allocation of a land plot, the issuance of an APL, the allocation of red building lines are determined by calculation and are included in columns 7 and 8.

    Initial design data, permits, technical specifications and requirements for connecting the designed objects to engineering networks and communications common use, carrying out the necessary approvals - on calculations and prices for these services (except for services budgetary organizations), and also according to the letter of the Gosstroy of Russia dated November 14, 1996 No. BE-19-30/12, (columns 7,8).

    1.2. Funds for laying out the main axes of buildings and structures and securing them with points and signs are determined by calculation based on the Collections of prices for survey work and are included in columns 7.8.

    Funds for carrying out construction work to secure points and signs in kind are determined by calculation based on the UPSS and are included in columns 4.8.

    1.3. Payment for land upon withdrawal (purchase) of a land plot for construction, as well as payment land tax(lease) during the construction period is determined on the basis of the Law of the Russian Federation “On Payment for Land” dated October 11, 1991 No. 1738-1 (as amended and additionally), the Land Code of the Russian Federation, Decree of the Government of the Russian Federation dated March 15, 1997 No. 319 “On the Procedure determining the standard price of land” (clause 8, appendix 8), based on the amount of land tax (tax rates) and the standard price of land (columns 7,8)

    1. Development of the construction area.

    2.1. Costs associated with compensation for demolished buildings and gardening plantings, compensation for losses to land owners, landowners, land users, tenants and losses of agricultural production are determined by calculation, based on the “Regulations on the procedure for compensation of losses to land owners, landowners, land users, tenants and losses agricultural production”, approved by Resolution of the Council of Ministers of the Government of the Russian Federation dated January 28, 1993 No. 77, taking into account amendments dated November 27, 1995 No. 1176 “On amendments to Resolution No. 77 dated January 28, 1993” (columns 7, 8).

    2.2. Costs associated with the development of the construction site and included in construction and installation work:

    Clearing the construction area from existing buildings and structures (demolition or relocation and construction to replace what is being demolished in another place).

    Cutting down forests and shrubs, uprooting stumps and removing waste from cutting down trees;

    Removal of waste and materials from dismantling that are unsuitable for further use;

    Restoration (reclamation) of disturbed lands provided for temporary use during the construction period, i.e. bringing these areas into a condition suitable for use in agriculture, forestry, and fisheries;

    Work related to the construction and reconstruction of reclamation systems.

    Determined on the basis of design data (scope of work) and current prices for local and site estimates (estimates) (columns 4, 5 and 8).

    Places for storage and removal of soil, garbage, materials from dismantling and cutting of plantings that are unsuitable for recycling, as well as quarries for the delivery of missing soil are established by the customer in accordance with the “Regulations on the customer during the construction of facilities for public needs in the Russian Federation”, approved by the Resolution of the State Construction Committee of Russia dated 06/08/01 No. 58, clause 3.1.3.

    In cases of reclamation at several geographically separated sites, funds for these purposes may be included in the corresponding site estimates (estimates) for the construction of specific buildings and structures.

    2.3. Work related to unfavorable hydrogeological conditions of the construction area and the need to create detours for urban transport.

    Determined in accordance with design data, hydrogeological survey data and PIC data according to local and site estimates (budget calculations) (columns 4 - 8).

    The amount of funds provided for in Chapter 1 “Preparation of the construction site” of the consolidated estimate should also take into account the cost of work necessary to accommodate temporary buildings and structures.

    The procedure for forming construction costs for chapters 2 - 7.

    Chapter 2 “Main construction projects” includes the estimated cost of buildings and structures and types of work for main production purposes.

    In ch. 3 “Objects for auxiliary and service purposes” includes the estimated cost of objects for auxiliary and service purposes:

    For industrial construction - buildings of repair and technical workshops, factory offices, overpasses, galleries, warehouses, etc.;

    For housing and civil construction - utility buildings, passageways, greenhouses, in hospital and scientific campuses, garbage dumps, etc., as well as the cost of buildings and structures for cultural and community purposes, intended to serve workers, located within the territory allocated for the construction of enterprises.

    In the case when a separate project is being developed, with a summary estimate of the cost of construction of such facilities as a boiler room, power supply line, heating networks, landscaping, roads, etc., which are usually indicated in Chapter. 3 - 7 SSR for a complex project, the estimated cost of these objects should be included in Ch. 2 as main objects.

    Chapters 4 - 7 include objects, the list of which corresponds to the title of the chapters.

    The procedure for determining the amount of funds for temporary buildings and structures included in Chapter 8.

    Chapter 8 of the consolidated estimate includes funds for the construction and dismantling of title temporary buildings and structures necessary for construction and installation work, as well as for servicing construction workers within construction site or a route allocated for construction, taking into account the adaptation and use for the needs of the construction of existing and newly constructed buildings and structures of a permanent type.

    The amount of funds intended for the construction of title buildings and structures may be determined:

    According to calculations based on PIC data in accordance with the required set of title temporary buildings and structures;

    - according to the standards established by the State Construction Committee, as a percentage of the estimated cost of construction and installation work based on the results of Chapters 1-7 of the SSR.

    Simultaneous use of these methods is not allowed. The amount of funds determined by one of these methods is taken into account in columns 4, 5 and 8.

    The limit of funds for the construction of temporary buildings and structures is determined according to the Collection of estimated cost standards for the construction of temporary buildings and structures (GSN 81-05-01-2001).

    The limit of funds for the construction of temporary buildings and structures during repair and construction work is determined according to the Collection of estimated cost standards for the construction of temporary buildings and structures during repair and construction work (GSNr 81-05-01-2001).

    The estimate standards specified in GSN 81-05-01-2001 can be used when drawing up estimate documentation for major repairs of industrial buildings, reconstruction and expansion of existing enterprises, buildings and structures, construction of subsequent phases on the territory of existing enterprises or adjacent sites using to the specified norms of the coefficient 0.8.

    The procedure for determining the amount of funds included in Chapter 9 “Other work and costs”.

    The main costs to be included in Chapter 9 are:

    -Winter price increases.

    -Voluntary insurance.

    Other work and costs are included in Chapter 9 if necessary and mainly based on PIC data.

    Additional costs when carrying out construction and installation work in winter are determined according to the standards of the Collections of estimated standards for additional costs when carrying out construction and installation work in winter (GSN 81-05-02-2001), when carrying out repair and construction work in winter (GSNr 81-05-02-2001). These standards are determined as a percentage of the cost of construction and installation work based on the results of chapters 1-8 for construction projects and 1-6 for major repair projects (columns 4, 5 and 8).

    In areas exposed to winds with speeds above 10 m/s, increasing coefficients confirmed by data from the current Russian Climate Handbook and certificates from local hydrometeorological service authorities can be applied to the amount of additional costs calculated according to the standards of the Collections.

    When the number of windy days with a wind speed of more than 10 m/s in winter exceeds 10%:

    St. 10% to 30% - 1.05;

    over 30% - 1.08.

    The above surcharge rates do not apply to capital repairs carried out without stopping the operation of buildings being repaired or in heated buildings, or consisting of eliminating faults in structures, finishing, engineering equipment inside the building while preserving the roof and window fillings.

    Maintenance costs existing permanent ones and their restoration after completion of construction highways are determined by local estimate calculations based on the PIC in accordance with the design scope of work according to collection No. 27 “Highways” (columns 4, 5 and 8).

    Transportation costs by car workers construction and installation organizations or compensation of expenses for organizing special routes of urban passenger transport are determined by calculations based on the PIC, taking into account the supporting data of transport enterprises (columns 7 and 8). The costs of transporting workers of construction and installation organizations by motor transport to the place of work and back are allowed to be included in the Consolidated Estimate Calculation in the case where the place of residence (collection point) of workers and employees is located at a distance of more than 3 km from the place of work, and public or suburban transport is either absent or unable to provide transportation for workers.

    Costs associated with carrying out work on a rotational basis determined by calculation based on the PIC (columns 7 and 8).

    Costs associated with the use of military construction units, student detachments and other contingents, as well as with the organized recruitment of workers, are determined by calculations based on the PIC (columns 7 and 8).

    Costs associated with sending workers for construction, installation and special construction work are determined by calculations based on the PIC or by the estimated labor intensity determined in the estimate documentation (columns 7 and 8), based on the distance to the construction site and the nature of the work performed.

    Costs associated with relocation construction and installation organizations from one construction site to another are determined by calculations based on the PIC (columns 7 and 8).

    Costs associated with input bonuses the commissioning of constructed facilities is determined from the estimated cost of construction and installation work of the consolidated estimate of the cost of construction by calculation according to the letter of the Ministry of Labor of Russia and the State Construction Committee of Russia dated October 10, 1991 No. 1336-VK/1-D and are indicated in columns 7 and 8.

    Costs associated with deductions to the research and development fund (R&D) accepted in the amount of 1.5% of the cost of construction products (columns 7 and 8) by agreement with the customer.

    Facilities to cover the costs of construction organizations on payments (insurance premiums) for voluntary insurance , including construction risks and are accepted in a total amount of up to 3% of the amount of construction and installation work in accordance with Decree of the Government of the Russian Federation of May 31, 2000 No. 420. At the same time, the total amount of deductions for voluntary insurance of construction risks cannot exceed 2% of the volume products (works, services) sold, and the total amount of deductions for insurance of employees against accidents and illnesses, health insurance and under agreements with non-state pension funds having a state license - 1% of the volume of products sold (works, services).

    Facilities for payment costs associated with leasing construction machinery, used in construction, installation and repair works are determined by calculation according to the letter of the State Construction Committee of the Russian Federation dated March 18, 1998 No. VB-20-98/12 (columns 7 and 8). When paying for completed construction and installation work, leasing payments without value added tax are included in the Certificates for completed work based on calculation of actual costs. Funds for leasing payments for technological (domestic and imported) equipment included in the estimates of construction sites, enterprises under construction, reconstruction, buildings and structures are not provided for in the estimate documentation, because These costs are included in the cost of products produced on this equipment after the facility is put into operation.

    Funds for organizing and conducting contract tenders(tender) are determined on the basis of calculations by type of cost in accordance with the letter of the Ministry of Construction of Russia dated February 19, 1996 No. VB-29/12-61 (columns 7 and 8).

    Costs of supporting government investment programs(provision of engineering services) are accepted in the amount of up to 0.15% of the cost of construction and installation work (columns 7, 8), according to the resolution of the State Construction Committee of Russia dated 06/03/93 No. 18-19.

    Costs of special measures to ensure normal working conditions(combating radioactivity, silicosis, etc.) are determined by calculation based on the PIC (columns 7 and 8).

    Costs of maintaining and operating environmental funds: wastewater treatment plants, ash collectors, wastewater treatment, etc. determined by calculation based on the PIC (columns 7 and 8).

    Fleet rental costs during the construction of bridges, offshore structures, etc. are determined by calculation based on the PIC (columns 7 and 8).

    Costs of renting special aviation equipment for construction and installation work are determined by calculation based on the PIC (columns 7 and 8).

    Costs of maintaining a mining rescue service are adopted on the basis of standards approved by the State Construction Committee of Russia and relevant agreements.

    Costs of monitoring settlement of buildings and structures during construction, erected on subsidence, permafrost, bulk soils, as well as unique objects, are determined by calculation based on design decisions and an observation program (columns 7 and 8).

    Costs of performing artistic works at construction sites by creative organizations are determined by calculation on the basis of contracts concluded with creative organizations (columns 7 and 8).

    Costs of passing storm and flood waters determined by calculations based on the PIC (columns 7 and 8).

    Costs of paying fees for transportation of oversized cargo on roads and bridges are determined by calculations based on the PIC (columns 7 and 8).

    Commissioning costs included for social facilities (children's institutions, schools, boarding houses). The amount of funds is determined on the basis of estimates for commissioning work (columns 7 and 8).

    In addition, the letter of the State Construction Committee of the Russian Federation dated October 27, 2003 No. NK-6848/10 determined the procedure for allocating costs for commissioning work from November 1, 2003 during the construction of new, expansion, reconstruction and technical re-equipment of existing enterprises, buildings and structures for housing, civil and industrial purposes. Costs for commissioning work “idle”, associated with bringing the facility to a state suitable for use, in accordance with the norms of the article Tax Code RF are taken into account as capital expenses and are included in Chapter 9 of the Consolidated Estimate (columns 7 and 8). When attributing the costs of commissioning work “idle” to capital investments, one should be guided by the structure of the full complex of commissioning work, taken into account in the new cost estimate and regulatory framework 2001, developed by the State Construction Committee of Russia. The list of works and costs included in Chapter 9 given above can be supplemented for construction, based on specific conditions and features.

    Work and costs included in chapters 1, 8 and 9 of the consolidated estimate, can constitute a significant proportion of the total estimated cost of construction and many of them are justified and included in the estimate documentation based on data POS. All this points to the special role of the PIC in the formation of the estimated cost of construction, since it is the PIC that reflects both the working conditions and all other requirements that affect the estimated cost, both in local and site estimates, and in the SSR.

    The procedure for determining the amount of funds for maintaining the customer-developer service under Chapter 10.

    The amount of funds for the maintenance of the customer-developer’s apparatus (technical supervision) is determined according to the standards established by the Decree of the State Construction Committee of the Russian Federation dated February 13, 2003 No. 17 (columns 7 and 8) for construction projects financed from federal budget.

    The procedure for determining the amount of funds for training operational personnel for enterprises under construction) under Chapter 11.

    Costs are determined by calculation in cases where new technologies are being mastered for which specialists are not trained in the education and training system (columns 7 and 8).

    The procedure for determining the amount of funds for design and survey work, designer supervision under Chapter 12.

    Cost of design and survey work for construction are determined on the basis of collections and reference books of basic prices developed by the Russian Gosstroy for construction sectors, recalculated to the current level according to indices established by the Russian Gosstroy.

    The cost of the examination of pre-project and design documentation is determined in accordance with the “Procedure for determining the cost of work to carry out the examination of pre-project and design documentation for the construction of enterprises, buildings and structures on the territory of the Russian Federation,” approved by Resolution of the State Construction Committee of Russia dated August 18, 1997 No. 18-44.

    The cost of development and examination of tender documentation is determined by calculations in agreement with the customer.

    The costs listed above are taken into account in columns 7 and 8 of the Consolidated Estimate.

    About the reserve of funds for unforeseen work and expenses

    The reserve is accrued based on the results of chapters 1-12 in the amount of no more than 2% for objects social sphere and no more than 3% - for industrial facilities (columns 4-8) and is intended to reimburse the cost of work and expenses, the need for which arises during the design or during construction as a result of clarifying design decisions or construction conditions for objects (types of work) provided for in the approved project.

    For unique and particularly complex construction projects, the size of the reserve of funds for unforeseen work and costs can be increased in each specific case in agreement with the State Construction Committee. Part of the reserve provided for in the consolidated estimate, in the amount agreed upon by the customer and contractor, may be included in fixed contract prices for construction products.

    Additional funds for reimbursement of costs identified after approval of project documentation in connection with the introduction of new legislative and regulatory acts should be included in the consolidated estimate. on a separate line(in the relevant chapters) with subsequent changes in the final construction cost indicators and approval of the changes made by the authority that approved project documentation, and for construction projects financed from the federal budget - in the manner established by the State Construction Committee of Russia.

    About the funds included at the end of the Consolidated Estimate.

    Following the results of chapters 1-12 of the Consolidated estimate and reserve for unforeseen work and costs, the following is shown:

    1. Refunds based on cost:

    Materials and parts obtained from dismantling temporary buildings and structures, regardless of the period of construction;

    Materials and parts obtained from dismantling structures, demolishing and moving buildings and structures, in the amount determined by calculation;

    Furniture, equipment and inventory purchased for furnishing residential and office premises for foreign personnel who supervise the installation of equipment;

    Materials obtained through incidental mining.

    The refundable amounts given after the results of the Consolidated Estimate Calculation are summed up from the totals of the refundable amounts shown for reference in the object and local estimates.

    1. Total based on the results of object and local estimates and estimates book value(residual) cost of equipment dismantled or rearranged within the existing reconstructed or technically re-equipped enterprise. In this case, the technical and economic indicators of the project are determined taking into account the full cost of construction, which also includes the cost of the rearranged equipment.
    2. Amounts of funds for equity participation. The principle of processing amounts equity participation as part of the estimate documentation for construction is given in Appendix 3 SP 81-01-94.
    3. Final data on the distribution of the total estimated cost of construction of a microdistrict or a complex of residential and public buildings by areas of capital investment, in the case where this construction includes built-in, attached or free-standing buildings and structures related to various areas of capital investment.

    The estimated cost of structures, devices and individual works included in the microdistrict or complex is distributed:

    For intra-block (yard) networks of water supply, sewerage, heat and energy supply, etc. - in proportion to the needs of the facility;

    For landscaping and landscaping of the territory - in proportion to the area of ​​the plots;

    In other cases - proportionally total area buildings (structures).

    1. The amount of value added tax (VAT).

    The amount of funds for the payment of VAT is accepted in the amount established by the legislation of the Russian Federation from the final data for the Consolidated Estimate Calculation for Construction and is shown in a separate line (columns 4-8) under the name “Funds to cover the costs of paying VAT.” At the same time, in order to avoid double counting, the accrual of VAT on the cost of materials and structures, equipment, as well as on transport and other types of services should not be taken into account in the local and site estimates (estimates) compiled. In cases where the legislation of the Russian Federation establishes benefits for the payment of VAT for certain types of construction projects, this line includes only the funds necessary to reimburse the costs of contract construction and installation organizations for paying VAT to suppliers. material resources and other organizations for the provision of services (including design and survey work). The amount of these funds is determined by calculation depending on the structure of construction and installation work.

    Sample

    (name of company)

    “Approved” “__” _________________ 20__

    Consolidated estimate in the amount of _____________________________________ thousand rubles.

    Including refundable amounts __________________________________________ thousand rubles.

    "__" ______________ 20__

    SUMMARY ESTIMATE CALCULATION OF THE COST OF CONSTRUCTION (Major REPAIRS)

    ___________________________________________________________________________

    (name of construction site (object being repaired))

    Compiled in prices as of ______________________________ 20__.

    Supervisor

    design organization ______________________________________________________________

    Chief Engineer

    project _____________________________________________________________________

    [signature (initials, surname)]

    Department head _______________________________________

    (name) [signature (initials, surname)]

    Customer ___________________________________________________________________

    [position, signature (initials, surname)]

    Approved

    Main purpose of the form: drawing up in the process of acceptance of completed contract construction and installation works for residential, industrial and other facilities.

    Compiled based on logs of work performed (form No. KS-6a).

    Subscribes authorized representatives of the parties who have the right to sign (work producers, customers, general contractors).

    Unified form No. KS-3 "Certificate of the cost of work performed and expenses."

    Approved Resolution of the State Statistics Committee of the Russian Federation on November 11, 1999 No. 100.

    Main purpose of the form: Used for settlements with the customer for work performed.

    Compiled in the required number of copies. One copy is for the contractor, the second is for the customer (developer, general contractor).

    Standard intersectoral form No. KS-6 "General work log".

    Approved Resolution of the State Statistics Committee of the Russian Federation dated October 30, 1997 No. 71a.

    Main purpose of the form: Used to record construction and installation work.

    Unified form No. KS-6a "Logbook of work performed."

    Approved Resolution of the State Statistics Committee of the Russian Federation on November 11, 1999 No. 100.

    Main purpose of the form: It is used to record work performed and is a cumulative document on the basis of which an acceptance certificate for work performed is drawn up in Form N KS-2 and a certificate of the cost of work performed in Form N KS-3. The work log is kept by the contractor for each construction project based on measurements of work performed and uniform standards and prices for each structural element or type of work.

    Form M-29.

    Approved Central Statistical Office of the USSR 11/24/1982 N 613.

    Main purpose of the form: serves as the basis for writing off materials for the cost of construction and installation work and comparison actual consumption building materials for completed construction and installation work with consumption determined according to production standards.

    Form No. 1 “Consolidated estimate of construction costs.”

    Main purpose of the form: is compiled to reflect the full cost of all work and expenses provided for by the project, including the estimated cost of construction and installation work, the cost of purchasing equipment, tools, inventory, as well as all related costs.

    Form No. 3-c “Object estimate calculation”.

    Main purpose of the form: determines the estimated limit for the construction of the facility as a whole by summing up data from local estimate calculations and local estimates.

    Form No. 4-c “Local estimate calculation”.

    Main purpose of the form: Designed to determine the estimated limit for separate species work (costs).

    Defective statement.

    Main purpose of the form: Used as a document recording expenses when carrying out repairs. Compiled in any form

    Act hidden work.

    Main purpose of the form: is compiled when performing construction and installation work, the quality of which cannot be controlled and assessed. These include hydro-, sound-, thermal insulation, repair of electrical wiring, installation of pipes, etc., which will be hidden by subsequent work behind walls and panels. The act of hidden work is confirmation that the work was performed to a high standard.

    Share